How to Create a Release Burn-Up Chart

A release burn-up chart is used to track team progress and to develop data-based forecasts that can be used to help balance trade-offs in achieving a release plan. Charting data should be updated with each iteration. This will keep forecasts current much like an NOAA hurricane landfall chart.

Release burn-up charts are built using summed measures of work over time. In Scrum, this could mean story points per sprint. However it can also be used with other frameworks like Kanban, for example as work items per week. There are tools that will generate these charts but my preference is to use a spreadsheet for more control over the content and delivery. Here we will use Microsoft Excel to develop the release burn-up chart assuming the development team has just completed sprint 6 and would like to forecast out another 9 sprints. Value is measured in story points.

The charts and tables can be downloaded as an Excel spreadsheet or as a pdf for reference.

Keep in mind

  • Make forecasts, not commitments.
  • Prepare to inspect and adapt.
  • Good data will take time to develop so just get started.
 
 

Start with velocity data, something the team is likely tracking already.


Create a spreadsheet using the velocity data and add a column to contain the story point summation. Plot iterations on the horizontal axis and the summed story points on the vertical axis. Extend the iteration count into the future.

Here, we are forecasting through sprint 15.


In a separate cell calculate the story point average for the last 3 sprints*. In this case:

(15 + 30 + 21)/3 = 66/3 = 22

Add a column to contain the forecast average and carry over the current sum for 'today' as a starting value. Forecast into the future summing the average over time.

Don't fall into the trap of mistaking a forecast for a commitment. It would be easy (and desirable) to state that the team will achieve 228 story points at the close of sprint 11. It is only a likely outcome if nothing changes and the last 3 sprints are an accurate indicator of future performance. Again, think weather...

* Forecasts should be based on recent history, rather than performance overall, simply because things change. 3 sprints are used as a rule of thumb, however use your judgement to assess how much history is relevant to the current work and team. When doing so, consider the contributing factors to change:

  • Team's focus, both what and how the product is being built
  • Team's capability to learn
  • Team membership

In a separate cell, calculate the standard deviation for the last 3 sprints. We will use this value to establish reasonable* upper and lower bounds for the forecast. Here,

σ = 7.55

Create columns for forecast highs and lows where the value is equal to the forecast value + or - the standard deviation. The deviation is additive as the forecast extends into the future. Plotting the high and low values in addition to the average forecast should demonstrate a cone of probability.

An alternative and perhaps simpler, non-statistical approach, is to use the average of the 3 highest sprints and 3 lowest sprints to establish the variance around the average. We are after accuracy, not precision, and this approach will suffice.

* We will assume the data is normal (fits a bell-curve) and won't change over time. These assumptions are not likely to hold true, however this approach should provide a good approximation. Given these assumptions and using a standard deviation on each side of the average will result in a 68% confidence level.


With a forecast in place it is a simple to evaluate what scope might be completed by a given time. In the example here, the team should be able to complete between 219 and 325 story points by the close of sprint 13.


Perhaps more common is the desire is to know when a given amount of work will be done. This can take the form of an MVP (minimum viable product) as is demonstrated here. To show this, plot the magnitude of the MVP over time. Note this value may change as the business responds to market need and capability of the team.

In this example, the MVP at 225 story points is likely to be achieved between sprints 10 and 14.


It is important to update the data on a regular basis, iteration boundaries being the most common time. In the example here, sprint 6 has moved to historical and 'today' is identified as sprint 7. Values have been updated, including the average and standard deviation for the last 3 sprints (sprints 4, 5, 6).

You may notice that the cone width has been reduced.  Greater predictability in the time is reflected in the smaller standard deviation, being reduced from 7.55 to 4.51.  This may stem from the team hitting its stride, increasing predictability and improving forecast variability.

Notice that the average velocity has gone up as well, from 22 to 25, and is seen as a slight 'tip up' of the cone. This coupled with increased predictability indicates achievement of the MVP as likely between the sprints 10 and 11.


The evolution of the forecast from sprint 6 to 7 can be seen in the short video below.

Previous
Previous

Minimally Marketable Feature